Sangshin Central Vietnam project is invested by Sangshin Central Vietnam Co., Ltd. and Dinco E&C was assigned by the investor to perform the role of design and build general contractor for the project.

After 7 months of construction, the project has completed 99% of the work volume. Currently it is entering the last stage of finishing. It is expected that in February 2023, the project will be handed over to the investor to put into production. Therefore, compared to the original goal, DINCO has fulfilled its commitment on schedule and quality.

One of the outstanding achievements of the project is the factory floor which is certified for FM1 flat floor, 34th Edition. Flat floors help bring many benefits in the operation and production process of businesses.