HAPPY DUNG QUAT PROJECT - PHASE 4 AHEAD THE CONSTRUCTION PROGRESS

HAPPY DUNG QUAT PROJECT - PHASE 4 AHEAD THE CONSTRUCTION PROGRESS

Up to now, the project has been implemented for 4 months, the Site Management Board of Happy Dung Quat - Phase 4 project has completed 80% of the work. Dinco is rushing to implement the final works such as concrete pouring, workshop foundation, and steel work. With the current progress, Dinco is confident to finish the project 1 month earlier than contracted but still ensure the highest quality.
Admin by Admin
  Updated July 23, 2022
SANGSHIN CENTRAL VIETNAM PROJECT FOR ACHIEVING THE SAFETY CERTIFICATE

SANGSHIN CENTRAL VIETNAM PROJECT FOR ACHIEVING THE SAFETY CERTIFICATE

Congratulations on SangShin Central VietNam project for achieving the safety cerificate of June 2022 Mạng thể thao bet365au (Việt Nam).
Admin by Admin
  Updated July 7, 2022
DINCO ACCOMPANYING DA NANG INVESTMENT FORUM 2022

DINCO ACCOMPANYING DA NANG INVESTMENT FORUM 2022

On the afternoon of June 25, 2022 at Sheraton Grand Danang Resort, Da Nang Investment Forum 2022 with the theme: "A year of safe, flexible adaptation, effective pandemic control, and economic-social recovery and development”, which was organized by the People's Committee of Da Nang City, attracted more than 600 domestic and foreign delegates and guests. Dinco Engineering and Construction Corporation is a companion contributing to the success of this forum.
Admin by Admin
  Updated June 27, 2022
VIDEO OF CONSTRUCTION PROGRESS OF CHAN MAY QUARTZ MACHINING FACTORY IN HUE AFTER 1 MONTH OF COMMENCEMENT

VIDEO OF CONSTRUCTION PROGRESS OF CHAN MAY QUARTZ MACHINING FACTORY IN HUE AFTER 1 MONTH OF COMMENCEMENT

Video of Construction progress of Chan May Quartz Machining Factory in Hue after 1 month of commencement. Update on 01.06.2022 Mạng thể thao bet365au (Việt Nam).
Admin by Admin
  Updated June 15, 2022
GROUND-BREAKING CEREMONY OF SANGSHIN CENTRAL VIETNAM PROJECT

GROUND-BREAKING CEREMONY OF SANGSHIN CENTRAL VIETNAM PROJECT

In the morning of June 1, 2022, at Ai Tu commune, Trieu Phong district, Quang Tri province, Dinco Engineering and Construction Corporation solemnly held the Groundbreaking Ceremony of Sangshin Central Vietnam project.
Admin by Admin
  Updated June 2, 2022
HOW IS THE PROGRESS OF HAPPY FURNITURE PHASE 4 PROJECT?

HOW IS THE PROGRESS OF HAPPY FURNITURE PHASE 4 PROJECT?

Happy Furniture Phase 4 project was started by Dinco General Contractor on February 11, 2022 and expected to be completed on August 31, 2022 Mạng thể thao bet365au (Việt Nam).
Admin by Admin
  Updated May 26, 2022